Why gross margin cannot tell you whether a job was good, and the one rate that makes it mean something.
Author: Joe Leone, CPA, MSA, Partner
I ask contractors how a job did. They almost always answer the same way. They give me the gross margin.
22%, one of them told me recently, and he was proud of it. It was a good number and he had earned it.
So I asked him the second question. What does a job at your company have to hit before it makes you anything?
He did not have an answer. Not because he is careless. Because nobody had ever built that number, and nobody had ever asked him for it.
Two numbers that live in separate rooms
In most construction companies, margin and overhead never meet.
Margin is a field conversation. It lives on the job cost report, it gets discussed job by job, and everyone from the project manager to the owner has an opinion about it.
Overhead is an office conversation. It gets calculated once a year, usually because the accountant needed it for something, and then it goes in a drawer.
Both numbers are accurate. Neither one is useful alone. Margin without overhead tells you what a job produced. Overhead without margin tells you what the company costs. Only the subtraction tells you whether the job was worth running.
What the rate actually is
Your overhead absorption rate is the share of every revenue dollar that has to go toward running the company before anything is left over for the company to keep.
It takes two figures you already have, pulled from the last twelve months.
- Direct job cost. Labor and burden, materials, subcontractors, equipment charged to jobs, permits. Anything that would not exist if the job did not exist.
- Indirect cost. Office and administrative salaries, nonbillable project management and estimating time, rent, insurance, software, vehicles not charged to a job, professional fees, marketing, and owner compensation that is not job related.
Take a contractor doing 8.4 million dollars a year.
| Twelve month summary | Amount | Percent of revenue |
|---|---|---|
| Revenue | $8,400,000 | 100.0% |
| Direct job cost | $6,300,000 | 75.0% |
| Gross profit | $2,100,000 | 25.0% |
| Indirect cost (overhead) | $1,680,000 | 20.0% |
| Net profit | $420,000 | 5.0% |
His overhead absorption rate is 1,680,000 divided by 8,400,000. 20%.
That is the line. Twenty cents of every revenue dollar is spoken for before the job contributes anything. A job at 20% gross margin breaks even. A job at 25% contributes 5 points. A job at 18% takes money out of the company no matter how busy the crew was or how happy the customer is.
Some contractors prefer the rate expressed against direct cost instead of revenue, because that is how an estimator thinks. Same overhead, different denominator. 1,680,000 divided by 6,300,000 is 26.7%, the markup on cost required to cover overhead. Both versions are correct. Use whichever one your estimators will actually apply.
The job that looked fine
Here is what the rate does to a job list everyone thought was healthy. Four jobs, all closed, all paid, nobody unhappy.
| Job | Contract | Direct cost | Gross profit | GP % | Overhead absorbed | Contribution |
|---|---|---|---|---|---|---|
| A | $1,200,000 | $900,000 | $300,000 | 25.0% | $240,000 | $60,000 |
| B | $640,000 | $524,800 | $115,200 | 18.0% | $128,000 | ($12,800) |
| C | $2,100,000 | $1,554,000 | $546,000 | 26.0% | $420,000 | $126,000 |
| D | $310,000 | $248,000 | $62,000 | 20.0% | $62,000 | $0 |
Job B is the one that started this. It closed at 18%. On the job cost report it sat in the middle of the pack, slightly below average but nothing that raised a hand. Once it absorbed its share of the company, it cost 12,800 dollars.
Nobody made a mistake on Job B. It was bid at a number the market would accept, it ran reasonably well, and the customer paid. It simply never had enough room in it to carry the company for the months it occupied a crew.
Job D is the more uncomfortable one. It landed exactly on the line. Months of work, real risk, real cash tied up, and the company finished exactly where it started.
Contrast
Contrast is what lets me see a shape at all. Not detail. Contrast.
A dark step against a light floor I can find. A white cup on a dark counter I can find. Take the contrast away and the object does not disappear. It blends into everything around it until I cannot tell where it starts.
Gross margin does that when there is no line underneath it. On the report, 18 and 25 look like the same kind of number. Both margin. Both positive. Both printed in the same column, in the same typeface, by the same system.
It takes the line underneath them to make one of them stand out as a problem.
That is the entire function of an overhead absorption rate. It is not more information. It is the background that makes the information you already have readable.
The second layer
For this contractor there was another layer underneath the first one, and it is the part I would want every reader to check against their own numbers.
Across his open jobs, earned revenue to date was 3,600,000 dollars against cost to date of 2,772,000. That is 828,000 of earned margin, or 23%. Against a 20% line it looked like a three point cushion. Thin, but positive, and everyone felt reasonably good about it.
Then we pulled out retainage.
Of that 3,600,000 of earned revenue, 360,000 was retained and could not be invoiced yet. On several of those jobs it could not be invoiced until the general contractor closed out the entire project. Every trade. Not just his scope.
| Open jobs | As reported | Billable today |
|---|---|---|
| Earned revenue to date | $3,600,000 | $3,240,000 |
| Cost to date | $2,772,000 | $2,772,000 |
| Margin | $828,000 | $468,000 |
| Margin percent | 23.0% | 14.4% |
| Overhead these jobs must carry at 20% | $720,000 | $720,000 |
| Coverage of overhead | $108,000 | ($252,000) |
Look only at what he could put on an invoice today and the margin on those open jobs was 14.4%, against overhead that still needed 20%. Overhead that goes out every Friday whether the retainage has been released or not.
In dollars, those jobs needed to carry roughly 720,000 of overhead and were producing 468,000 of billable margin to do it. The difference was being covered by the line of credit, which is exactly why the line of credit kept creeping up in a year the income statement called profitable.
That is not a margin problem anymore. That is a cash flow problem wearing a margin problem’s clothes.
A note on what this calculation is and is not
The second view is not a restatement of his financial statements and it is not a forecast of how the jobs will finish. It is a cash lens laid over the same jobs, and it answers a different question than the income statement does. Both views are true. Only one of them explains the line of credit.
What changes once you have the number
The rate is not an analysis you run once and admire. It is a line you install in four places.
The bid floor
Estimators get a minimum margin below which a job needs an owner’s signature. Not a preference. A floor. It does not mean you never go below it. It means going below it becomes a decision instead of an accident.
The job cost report
Add one column showing margin against the floor. Not the margin. The distance from the line. That is the column people actually read, because it tells them how much room is left rather than where things stand.
The go or no go conversation
A job that clears the floor by half a point is not a small opportunity. It is a job that will consume a crew for four months and return almost nothing, and it should have to compete against the option of not taking it at all.
Breakeven revenue
Overhead divided by gross margin percentage. For this contractor, 1,680,000 divided by 25% is 6,720,000 dollars of revenue just to cover the building. He runs 8.4 million, so roughly eight months of his year go to covering the company and four go to earning. Every person on the leadership team should be able to say that number out loud.
Keeping the number honest
An overhead rate built on last year’s volume will quietly lie to you the moment the volume changes. If revenue drops and overhead does not, the real rate climbs, and the bid floor you set in January is too low by June.
- Recalculate at least quarterly, and immediately after any real change in headcount, equipment, or volume.
- Track overhead as a percentage of revenue over time, not just at budget season. Overhead creeping up while volume stays flat is a warning even when no single line item looks alarming.
- Apply the rate per job the same way you apply labor burden, not as a year end allocation exercise.
- Keep the definition of direct and indirect stable. Moving a project manager’s salary between the two categories changes the rate without changing anything about the business.
The whole fix was one column
The contractor at the beginning of this article was not running a bad company. He was running a company that could tell him what happened and could not tell him what needed to happen.
A margin number on its own is a shape with no contrast behind it. Put the line underneath it and the same report you have been reading for years starts telling you which jobs were worth running.
He did not need a new system. He needed one number, and one column.